The maintenance is complete without power interruption.

------
Customer,

Shutdown maintenance for DRUPS has been scheduled in SG1 datacentre.

Date : 23rd April 2018
Maintenance Time : 08:00 Hrs to 22:00 Hrs (GMT+8)

During the shutdown maintenance:

1. DRUPS will be transferred to bypass mode and unit will be shut down. Power to one side of IT Racks will be on utility mains supply.

2. Suite cooling will not be affected.


The maintenance will affect colocation customers whose devices come with single power unit. There will be no impact for shared hosting and VPS servers.

An Email will be sent to you if your devices will be shut down.

Should you have any questions, please open a ticket.



Tuesday, April 10, 2018